Scrum SPS certification exam is an excellent opportunity for professionals who are looking to advance their careers in the software development industry. Certified Scaled Professional Scrum (SPS) certification demonstrates a candidate's expertise in Scrum frameworks and provides them with the necessary skills and knowledge to lead and manage large-scale software development projects using Scrum methodologies. With the Scrum SPS certification, professionals can differentiate themselves in a competitive job market and demonstrate their commitment to excellence and quality in Scrum frameworks.
Scrum SPS exam is essential for individuals looking to specialize in Scrum project management at a higher level. Certified Scaled Professional Scrum (SPS) certification is ideal for professionals proficient in Scrum, who aspire to lead or manage large-scale projects. It is a validation of individuals' knowledge, skills, and experience in Scrum, and provides them with the necessary resources to improve their leadership capabilities. Certified Scaled Professional Scrum (SPS) certification sets a standard for employers seeking individuals with Scrum expertise and the ability to manage complex projects successfully.
NEW QUESTION # 28
Karen was new to Scrum when the product development started. After 7 Sprints, she gained a lot of experience as a team member and would like to join the Nexus Integration Team. Is she a good candidate to be part of NIT?
- A. Yes, because Karen is now an experienced team member
- B. No, NIT members require several years of experience in Scrum
- C. No, because internal team members cannot be part of NIT
- D. No, because NIT membership remains same from Sprint 1 to last Sprint
Answer: A
NEW QUESTION # 29
Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 30
There can be two product backlogs in a Nexus. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 31
Can a specialist outside of Nexus join Nexus Integration Team? Yes or No?
- A. No
- B. Yes
Answer: B
NEW QUESTION # 32
Who coaches and guides the Scrum Team in the application of Nexus?
- A. Scrum Integration Team
- B. Nexus Integration Team
- C. Project Manager
- D. Product Owner
Answer: B
NEW QUESTION # 33
Nexus Integration team has defined a Definition of Done with 5 point criteria. One of the Sprint Team, want to use only 3 of them for their team's Definition of Done. Is this allowed?
- A. No
- B. Yes
Answer: A
NEW QUESTION # 34
Which two statements best describe Nexus Sprint Goal?
- A. Nexus Sprint Goal is optional whereas individual team's Sprint goal is mandatory
- B. Nexus Sprint Goal describes the purpose that will be achieved by the Scrum Teams during the Sprint
- C. Nexus Sprint Goal is the sum of all the work and Sprint Goals of the individual Scrum Teams within the Nexus
- D. Nexus Sprint Goal holds little value as long as the positive feedback is received from stakeholders
Answer: B,C
NEW QUESTION # 35
How many product backlogs should be maintained in a Nexus?
- A. Two per team
- B. Depends on the product
- C. One per team
- D. One
Answer: D
NEW QUESTION # 36
Teams want to integrate the code only before the Nexus Sprint Review.
What can be the result of this? Select all that apply.
- A. There may be too little time to resolve integration issues
- B. It will save Nexus members time
- C. Integrated Increment may not be available in time
- D. There may be too many code conflicts while integration
Answer: A,C,D
NEW QUESTION # 37
The Nexus Integration Team is responsible for a Definition of Done. True or False?
- A. TRUE
- B. FALSE
Answer: A
NEW QUESTION # 38
How does Technical Debt impact the product?
- A. It'll get difficult to add new features
- B. It leads to false assumptions about the state of the product
- C. It'll take longer to solve the existing bugs
- D. It'll get difficult to get additional funding for the product
Answer: A,B,C
NEW QUESTION # 39
Nexus requires the overall architecture to be designed and finalized before the Sprints can begin. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 40
You are part of Team A which is working on requirement #3. Team B is working on Requirement #6 which is very similar to yours. Your team discovered a limitation which would make it impossible to implement requirement #3.
When and who should you inform?
- A. Bring it up in Nexus Sprint Review
- B. Bring it up in Nexus Daily Scrum
- C. Wait for Team B to discover the issue on their own
- D. Bring it up in Nexus Sprint Retrospective
Answer: B
NEW QUESTION # 41
Who is accountable for a releasable integrated Product being delivered at least once at the end of every Sprint?
- A. Scrum Master
- B. Nexus Integration Team
- C. Every Team member
- D. Product Owner
Answer: B
NEW QUESTION # 42
How many parts are in Nexus Sprint Retrospective?
- A. 0
- B. 1
- C. Depends on the Nexus team
- D. 2
Answer: C
NEW QUESTION # 43
Who is not allowed to participate in Nexus Daily Scrum?
- A. NIT members
- B. Scrum Master
- C. Stakeholders
Answer: C
NEW QUESTION # 44
What is the technical debt?
- A. The money spent on the project so far
- B. Technical Debt may represent additional cost a team may incur due to poor design of code
- C. The money sponsor will lose if the project fails
- D. The money invested on the infrastructure of the project
Answer: B
NEW QUESTION # 45
Which is the main concern of developers when working in a Nexus?
- A. Cross-team refinement
- B. Managing dependencies
- C. Making sure there is no risk
Answer: B