NEW QUESTION # 83
The bus transportation system, represented by the American Bus Association has established an American Action Plan designed to improve safety and safety for bus operations. The goals of this plan are all of the following EXCEPT:
- A. To assist companies in developing infrastructures
- B. To protect the transportation infrastructure
- C. To promote security vigilance among operators through training and partnership with law enforcement agencies
- D. To preserve the bus industry as a strategic transportation reserve
Answer: A
NEW QUESTION # 84
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
- A. The activities are independent, with Activity 4001 starting 15 days earlier than the start of Activity 5001
- B. These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity
3001. - C. These activities are partially concurrent, with Activity 4001 starting 15 days after the start of Activity 3001
Answer: C
Explanation:
Relationship Analysis:
* Activity 4001 starts 15 days after Activity 3001 begins, based on their logical dependency (SS +15).
* This indicates partial concurrency, as both activities overlap in execution.
Evaluation of Other Options:
* A: Incorrect, as the statement refers to Activity 5001, not 3001.
* C: Incorrect, as Activity 4001 does not start before Activity 3001.
Verification with PSP Guidelines:PSP guidelines stress precise interpretation of activity relationships (Ref:
PSP Study Guide, Chapter 2A: Logical Relationships and Lags).
NEW QUESTION # 85
How many workdays occur from the start of the Product Testing to the Product Available milestone?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
Explanation:
The number of workdays between two milestones, such as Product Testing and Product Available, is calculated by considering the activity durations, dependencies, and any calendar constraints (PSP Study Guide, Subchapter 2.2.3, "Durations"). If the activities are continuous and there are no interruptions such as holidays, the total duration would sum to 100 days based on the provided schedule.
NEW QUESTION # 86
What is a major management function in business worldwide?
- A. Projection
- B. Quality
- C. Security
- D. Mission
Answer: C
NEW QUESTION # 87
Which of the following is NOT required when performing weekly or monthly schedule updates?
- A. Original duration of activities.
- B. Actual finish of activities.
- C. Remaining duration of activities.
- D. Percent complete.
Answer: A
NEW QUESTION # 88
Free float is the
- A. Amount of time the early start of an activity can be delayed without impacting the early start of the successor activity.
- B. Difference between the early finish dates and late finish dates of an activity.
- C. Difference In float value of the critical path activities and the float value of the specific activity being analyzed.
- D. Difference between the early dates and late dates of an activity.
Answer: A
NEW QUESTION # 89
A system in which installation circuits are connected to local police or fire departments or 911 centers by leased telephone lines is called;
- A. Auxiliary system
- B. Proprietary system
- C. Local alarm system
- D. Central station
Answer: A
NEW QUESTION # 90
Coverage of what provides remuneration for losses due to employee dishonesty?
- A. Surety Bonds
- B. 3-D policies
- C. Fidelity Bonds
- D. Insurance against loss of use
Answer: C
NEW QUESTION # 91
To deal with the lack of security, both government organizations have developed guidelines for protecting electric facilities and distribution systems. On the private side, the Edison Electric Institute developed guidelines that have been passed on to the North American Electric Reliability Council (NERC), the U.S. Department of Energy's coordinator for the U.S. electrical infrastructure. Among other things the guide lines cover:
- A. Threat response
- B. Cyber scenario
- C. Vulnerability/risk analysis
- D. Emergency detection
Answer: A,C
NEW QUESTION # 92
What is the remaining work duration of Active D?
- A. 3.
- B. 8.
- C. 0
- D. 4.
Answer: B
Explanation:
* Understand the Relationship Between G and H:
* The time-scaled diagram shows that Activity H starts immediately after the finish of Activity G.
* This is indicative of a Finish-to-Start (FS) relationship.
* Cross-Verification:
* Option A: Incorrect. The relationship is visible in the diagram.
* Option B: Incorrect. There is no evidence of a Start-to-Start (SS) relationship.
* Option D: Incorrect. Finish-to-Finish (FF) is not applicable here.
* Option C: Correct. FS relationship matches the network logic.
NEW QUESTION # 93
What is the authorized physical invasion of property or remaining on property after permission has been rescinded?
- A. Verdict
- B. Trespass
- C. Prosecution
- D. None of the above
Answer: B
NEW QUESTION # 94
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?
- A. 10 days.
- B. 15 days.
- C. 0 days.
- D. 5 days.
Answer: D
NEW QUESTION # 95
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?
- A. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity
6002. - B. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag
- C. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002
- D. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001
Answer: D
NEW QUESTION # 96
Identify the minimum project duration.
- A. 20 months.
- B. 19 months.
- C. 21 months.
- D. 16 months.
Answer: A
NEW QUESTION # 97
Which of the following is NOT input data to the construction planning process?
- A. The contract
- B. Input from the contractor
- C. Bonding capacity of subcontractors
- D. Input from the owner
Answer: C
NEW QUESTION # 98
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
- A. Estimate at completion (EAC)
- B. Budget at completion (BAC)
- C. Budgeted cost of work performed (BCWP)
- D. Estimate to complete (ETC)
Answer: D
NEW QUESTION # 99
Estimate to complete (ETC) is __________________.
- A. The expected total cost of an activity, group of activities or the project
- B. The costs actually incurred in accomplishing the work performed
- C. The expected remaining cost needed to complete an activity, group of activities or the project
- D. The value of the completed work expressed in terms of the budget assigned to that work
Answer: C
NEW QUESTION # 100
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It doesn't account for interdependent between activities.
- B. It requires a backward pass to calculate late dates.
- C. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- D. It assumes that resources are unlimited.
Answer: D
NEW QUESTION # 101
......