NEW QUESTION 78
Which type of Profitability Analysis updates the cost of goods sold at the time of delivery?
- A. Both account-based and costing-based only
- B. Periodic accounting-based
- C. Costing-based only
- D. Account-based only
Answer: D
NEW QUESTION 79
How do you maintain number intervals/ranges in Controlling?
- A. By posting key
- B. By company code
- C. By document type
- D. By business transaction
Answer: D
NEW QUESTION 80
What can you analyse in detail when you transfer the cost componentsplit from product cost planning to costing-based CO-PA?
- A. Cost of good sold
- B. Variance categories
- C. Cost of goods manufactured
- D. Sales revenues
Answer: A
NEW QUESTION 81
What action do you perform to use the Cost-Based Percentage of Completion (POC) method?
Response:
- A. Running the results analysis
- B. Costing of an order
- C. Billing of a sales order during production
- D. Setting to profitability analysis
Answer: A
NEW QUESTION 82
Which key performance indicators (KPIs) does profit center accounting help you report?
There are TWO correct answers for this question
Response:
- A. Profit contribution of a department
- B. Contribution of new customers to gross revenue
- C. Impact on sales of a marketing activity
- D. Return on capital expenditure investment
Answer: A,D
NEW QUESTION 83
What can you specify when you create an activity type?
There are THREE correct answers for this question
Response:
- A. The secondary costs G/L account for internal activity allocation
- B. The primary costs G/L account for internal activity allocation
- C. The valid receiving cost center types
- D. The valid sending cost center types
- E. The activity type category for allocation
Answer: A,D,E
NEW QUESTION 84
Which object do you configure to reuse material cost estimate for the costing process?
- A. Group costing
- B. Transfercontrol
- C. Quantity structure control
- D. Valuation variant
Answer: B
NEW QUESTION 85
When you define assessment cycles for the period-end closing in overhead cost accounting, which object can you assign to the cycle segment?
- A. Template
- B. Settlement rule
- C. Costing sheet
- D. Allocationstructure
Answer: D
NEW QUESTION 86
When do you select the percentage method for accrual calculation?
There are TWO correct answers for this question
Response:
- A. When you accrue activity-independent costs and an appropriate cost element for defining overhead rates is available
- B. When you accrue activity-dependent costs and an appropriate cost element in NOT available
- C. When you accrue activity-independent costs and an appropriate cost element is NOT available
- D. When you accrue-dependent costs and an appropriate cost element for defining overhead rates is available
Answer: A,D
NEW QUESTION 87
In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer
- A. Both WIP and variances or only variances
- B. WIP at planned costs or variances
- C. WIP at actual costs or variances
- D. WIP at target costs or variances
Answer: C
NEW QUESTION 88
What is the default option for planning profit center values in SAP S/4HANA?
Response:
- A. Management accounting planning
- B. Profitability analysis planning
- C. Financial accounting planning
- D. Business planning and consolidation
Answer: D
NEW QUESTION 89
Plan revenu = 3000 Plan costs = 2000 Actual revenue = 1200 Actual costs = 1000
- A. Revenue = 1200; Cost of sales = 800; Reserve = 200
- B. Revenue = 1200; Cost of sales = 1000; WIP = 200
- C. Revenue = 1200; Cost of sales = 800; WIP = 200
- D. Revenue = 1200; Cost of sales = 1000; Reserve = 200
Answer: C
NEW QUESTION 90
What can you define for a user status in the status profile?
- A. The assigned user status after a business transaction is executed
- B. The business user IDs authorized to change the user status
- C. The order types for which a user status is valid
- D. The versions for which you can enter plan data
Answer: A
NEW QUESTION 91
Which scenarios can be covered by the costing run?
- A. Inventory cost estimate of all thematerials in one plant
- B. Product cost collector cost estimate in one plant
- C. Current cost estimate of all the materials in all controlling areas
- D. Standard cost estimate of all the materials in all plants of a controlling area
Answer: C,D
NEW QUESTION 92
Which process determines the targetcosts of the cost object in a product cost by order scenario?
- A. Work in process (WIP) calculation
- B. Actual costscalculation
- C. Variance calculation
- D. Accrual calculation
Answer: C
NEW QUESTION 93
......
C_TS4CO_1909 Exam Certification Details:
| Duration: | 180 mins |
| Exam: | 80 questions |
| Sample Questions: | SAP C_TS4CO_1909 Exam Sample Question |
| Languages: | German, English, Spanish, French, Japanese, Korean, Russian, Chinese |
| Cut Score: | 63% |
| Level: | Associate |
Authentic Best resources for C_TS4CO_1909 Online Practice Exam: https://www.passreview.com/C_TS4CO_1909_exam-braindumps.html